| Description: | A high quality warehouse and office building located adjacent to Eastern Creek Raceway in Western Sydney.
The Mobis building comprises a 30,000 sq m warehouse with 2,000 sq m of fitted out office. The warehouse can be extended by another 10,000 sq m. The warehouse has very narrow aisles with wire guidance technology, high reach forklifts and very tight floor tolerances The building warehouses spare parts for Hyundai and Kia motor vehicles. |
|
| Client: | Mobis Parts Australia Ltd | |
| Dates: | 2006 to 2009 | |
| Site Area: | 6.1 hectares | |
| Value: | $50 million plus | |
| Our Role: | Project Management Joint Venture
George Birdsall worked with the experienced architectural project consultant Peter Altona advising Hyundai on all aspects of the project from Land Purchase to Design to Construction to Fitout to Occupation. George focused on the cost, budget and construction elements and Peter Altona on approvals and architectural issues. |